PROJECT DETAILS

Excavation : 226,000 cum

Concrete : 120,600 cum

Reinforcement Steel : 5,500 MT

River Diversion:

  • Coffer Dam : 15,000 cum
  • Cunnettes : 12,000 cum

Filters : 3,900 cum

Purpose : Hydro Power Generation (120 MW)

Client : Himachal Pradesh State Electricity Board, Shimla, India

23 Metre high concrete Diversion Dam/Barrage, intake structure with undersluices, spillweir and gates, desilting tanks with underground silt ejecting pipes, storage reservoir, coffer dams and other appurtenant works in Kinnaur District, Himachal Pradesh, India.

ENGINEERING CONSTRUCTION

The Construction work was carried out in extreme cold weather conditions and the project area remains snow bound for 4 months in a year. The Works were carried out at an elevation of 2450 Meters above MSL, which is the highest elevation at which a project of this nature has been constructed in the country.